Ausnutria Hyproca B.V.

2 years 2 months
Startup-manager
October 2017 – December 2017 (3 months)

Projectmanager
January 2016 – October 2017 (1 year 10 months)

Project Engineer
November 2015 – December 2015 (2 months)

Start up manager of:
Three Dry Blending (high volumes)
Two Pre-mix line, new designed equipment (semi-automatic, preparation,
collecting, macro’s and
micro’s and mixing.

Projectmanager:
Work activities and deliverables:
The Scope of Work (SOW) for a new dairy factory in Heerenveen, The
Netherlands. I am responsible for four projects:
FED to FAT installation;
SAT & start up;
Validation; IQ (Walkdown) OQ
Commercial production PQ and handshake to operations.

Supply of work:
Two Pre-mix line (apotheek, collecting macro’s and micro’s and mixing)
Three Dry Blending
Two Canning & filling line (high speed tin cans sizes 99 , 127 and 153 mm)
BIB (Bag in Box) line (on-going project)

Project Engineer:
Work activities and deliverables:
Review the scope of work
Pre-mix
Dry Blending
Canning line & filling
BIB (Bag in Box) line